Passer au contenu principal

Projects started before March 20, 2014

The procedure and Program terms and conditions in effect before March 20, 2014, will apply to projects that comply with the following three conditions:

  1. A letter of intent was sent before March 20, 2014, and the work related to eligible energy efficiency measures began before March 20, 2014 in accordance to point 2 below.
  2. The order for equipment needed for eligible energy efficiency measures was issued prior to March 20, 2014 (purchase order or invoice showing order date)
    or
    the first contract for work on eligible energy efficiency measures was signed prior to March 20, 2014.
  3. The request for payment of financial assistance sent to Hydro-Québec is accompanied by copies of the above-mentioned documents.

Note: Any projects started before March 20, 2014 that do not meet the three conditions stated above are subject to the procedures and conditions applicable as of March 20, 2014.

General documentation

Forms

Close  window