Title: Stage 2: By-pass Tunnel

The temporary diversion at the dam site is achieved by means of a tunnel excavated beneath the left bank of the Eastmain River. The tunnel makes it possible to temporarily dewater a short section of the riverbed for construction of the main dam. Once the tunnel gates have been closed, a concrete plug inside the tunnel, beneath the dam axis, will permanently seal the By-pass tunnel.

Shape Inverted U-channel
Tunnel dimensions (H x W) 18.4 x 14 m
Length 350 m
Peak flow
(based on a 40-year spring flood)
3,100 m3/s
Gate dimensions (H x W) 21 x 6.5 m