May 2016

  • Control building: testing all equipment installed in the building
  • Installing the upstream bridge on the spillway
  • Backup generators: installation and testing

April 2016

  • Control building: electrical, heating, ventilation, air conditioning and telecommunications work
  • Testing the emergency lifting mechanism on the spillway gates
  • Backup generator: cable pulling
  • Generating station: electrical work
  • Dismantling the temporary shelter at the control building

March 2016

  • Control building: roof and exterior cladding, interior finishing, installation of fire protection system, electric work
  • Completion of duct installation beneath the spillway deck
  • Cable pulling

January to February 2016

  • Duct installation beneath spillway deck
  • Cable pulling
  • Erection of new control building on the spillway

November to December 2015

  • Concreting of the foundations of the future generator installed near the generating station, on the Saint-Étienne-des-Grès side
  • Installation of a temporary winter shelter to be used during the construction of the new control building on the spillway
  • Start of duct installation beneath the spillway deck