The following slide show contains images from: Limoilou substation

  • Week of November 30, 2015 – Construction starts with formwork for the duct bank that will connect the future generator installed near the generating station on Saint-Étienne-des-Grès side.
  • Week of December 7, 2015 – Formwork for foundations of future generator.
  • Week of December 7, 2015 – Installation of the frame and supports for the ducts that will be used to connect the generator.
  • Week of December 14, 2015 – Construction begins on the temporary winter shelter to protect workers while the new control building is being built on the spillway.
  • Week of January 11, 2016 – Temporary shelter to protect workers through the winter construction of the control building.
  • Week of January 18, 2016 – Duct installation beneath the spillway deck to connect the generator that will be set up near the generating station.
  • Week of February 8, 2016 – Concrete slab curing in the future control building located on the spillway.
  • Week of February 15, 2016 – Concreting of control building crown.
  • Week of February 15, 2016 – Protective equipment set up in preparation for masonry to be carried out on the control building.