Power transmission – Integration of wind farms

120-kV De L'Érable Wind Farm Line

At a Glance
Status: Pending authorization
Region: Centre-du-Québec
Type: Growth in needs
Owner: Hydro-Québec TransÉnergie
Documents

In French only

De L'Érable

De L'Érable

The 100-MW De L'Érable wind farm is one of fifteen projects selected in Hydro-Québec's second call for tenders for the purchase of wind power.

To integrate generation from the future wind farm into its transmission network, Hydro-Québec must build a line segment about 12 km long. The segment will connect the wind farm, located in the De L'Érable RCM municipalities of Saint-Ferdinand, Sainte-Sophie-d’Halifax and Saint-Pierre-Baptiste, to the Bois-Francs–Plessisville line.

Construction is scheduled for winter 2010-2011, with commissioning in fall 2011.

To learn more about the project, consult the Documents section above.

Hydro-Québec's Home Page | Residential Customers | Business Customers | Energy Efficiency | Power Safety | Vegetation | Free Guided Tours | Learning | Corporate Profile and Publications | Press Releases | Sustainable Development | Construction Projects | Jobs [in French only] | Suppliers | Investors | Confidentiality and security