Power Transmission Projects
| Status: | Under construction |
| Region: | Montérégie |
| Type: | Long-term operability |
| Owner: | Hydro-Québec TransÉnergie |
| travaux dirigés par : | Hydro-Québec Équipement |
Existing Delson substation
Hydro-Québec is rehabilitating Delson substation in response to present and expected demand growth in and around the regional county municipality of Roussillon. The project mainly consists in adding and replacing equipment, and will take place entirely on Hydro-Québec property.
The work will go on for two years, from May 2009 to December 2010, and will cost over $17 million.
To find out more about this project, consult the PDF (available in French only) by clicking on the link above.