Power Transmission Projects
| Status: | Under construction |
| Region: | Nord-du-Québec |
| Type: | Growth in energy requirements |
| Owner: | Hydro-Québec TransÉnergie |
| Project supervision: | Hydro-Québec Équipement |
The line route is in the municipality of Baie-James.
As part of the Éléonore project, Opinaca Mines is currently prospecting on the northeast side of Opinaca reservoir.
At the promoter's request, Hydro-Québec conducted draft-design studies for the following:
The ideal solution in this context would be to build a 63.5-km line that could initially be operated at 69 kV and subsequently converted to 120 kV. Using the same line instead of building a second permanent line will substantially reduce the environmental impacts of the project.
Construction started in October 2009. Commissioning of 69-kV service is planned for 2010, followed by commissioning of 120-kV service in 2011 if the mining project goes ahead.
The estimated cost of the project is $29.7 million.
To learn more about the project, consult the Documents section above.