Power Transmission Projects

Integration of Wind Farms – 1st call for tenders (2003)

At a Glance
Status: Under study and under construction
Region: Bas-Saint-Laurent-Gaspésie
Type: Growth in energy requirements
Owner: Hydro-Québec TransÉnergie
Project supervision: Hydro-Québec Équipement
Documents
Wind mill

In October 2004, following a first tender call for the purchase of wind power, Hydro-Québec announced the acceptance of eight bids totalling 990 MW.

To ensure safe, reliable transmission of electricity produced by the eight new wind farms, Hydro-Québec Équipement will do a great deal of work on the Gaspé transmission grid (special protection systems, telecommunications, lines and substations).

To integrate the planned facilities harmoniously with their surroundings, Hydro-Québec will conduct technical, economic and environmental studies within the study areas. The company will also hold information and consultation sessions with stakeholders and citizens.

1. New lines

* In French only

 

2. Reinforcement of existing lines

  • 230-kV Les Boules–Matane line (under construction)
  • 230-kV Matane–Goémon line (under construction)

Hydro-Québec's Home Page | Residential Customers | Business Customers | Energy Efficiency | Power Safety | Vegetation | Free Guided Tours | Learning | Corporate Profile and Publications | Press Releases | Sustainable Development | Construction Projects | Jobs [in French only] | Suppliers | Investors | Confidentiality and security