Power transmission – Integration of wind farms

315-kV Lac-Alfred Wind Farm Line

At a Glance
Status: Under construction
Region: Bas-Saint-Laurent
Type: Growth in needs
Owner: Hydro-Québec TransÉnergie
Project supervision: Hydro-Québec Équipement et services partagés
Documents
Lac-Alfred

Lac-Alfred

The 300-MW Lac-Alfred wind farm is among fifteen projects selected in Hydro-Québec's second call for tenders for the purchase of wind power.

To bring the wind farm's output onto its transmission grid, Hydro-Québec must build a 315-kV single-circuit line segment 29.9 kilometres from the wind farm developer's substation to the Rimouski–Matapédia line.

Land clearing began in September 2011, and construction is scheduled to start in winter 2011-2012. Commissioning is planned for summer 2012.

To learn more about the project, consult the Documents section above.

Hydro-Québec's Home Page | Residential Customers | Business Customers | Energy Efficiency | Power Safety | Vegetation | Free Guided Tours | Learning | Corporate Profile and Publications | Press Releases | Sustainable Development | Construction Projects | Jobs [in French only] | Suppliers | Investors | Confidentiality and security