Power transmission – Integration of wind farms
| Status: | Under construction |
| Region: | Bas-Saint-Laurent |
| Type: | Growth in needs |
| Owner: | Hydro-Québec TransÉnergie |
| Project supervision: | Hydro-Québec Équipement et services partagés |
Lac-Alfred
The 300-MW Lac-Alfred wind farm is among fifteen projects selected in Hydro-Québec's second call for tenders for the purchase of wind power.
To bring the wind farm's output onto its transmission grid, Hydro-Québec must build a 315-kV single-circuit line segment 29.9 kilometres from the wind farm developer's substation to the Rimouski–Matapédia line.
Land clearing began in September 2011, and construction is scheduled to start in winter 2011-2012. Commissioning is planned for summer 2012.
To learn more about the project, consult the Documents section above.