Power transmission – Integration of wind farms

230-kV New Richmond Wind Farm Line

At a Glance
Status: Under construction
Region: Gaspésie–Îles-de-la-Madeleine
Type: Growth in needs
Owner: Hydro-Québec TransÉnergie
Project supervision: Hydro-Québec Équipement et services partagés
Documents
New Richmond

New Richmond

The 66-MW New Richmond wind farm is among fifteen projects selected in Hydro-Québec's second call for tenders for the purchase of 2,000 MW of wind power.

To bring the output from the New Richmond wind farm onto its transmission grid, Hydro-Québec must build a 230-kV single-circuit line about 10 km long from the substation owned by the wind farm developer, Venterre, to its Cascapédia substation.

Construction is scheduled for winter and spring 2012, with commissioning in summer 2012.

To learn more about the project, consult the Documents section above.

Hydro-Québec's Home Page | Residential Customers | Business Customers | Energy Efficiency | Power Safety | Vegetation | Free Guided Tours | Learning | Corporate Profile and Publications | Press Releases | Sustainable Development | Construction Projects | Jobs [in French only] | Suppliers | Investors | Confidentiality and security

© Hydro-Québec, 1996-2012. All rights reserved.