Power Transmission Projects
| Status: | Under construction |
| Region: | Nord-du-Québec |
| Type: | Growth in energy requirements |
| Owner: | Hydro-Québec TransÉnergie |
| Project supervision: | Hydro-Québec Équipement |
The purpose of this project, in the Nord-du-Québec region, is to transmit electricity generated at the new Sarcelle powerhouse to Hydro-Québec TransÉnergie's 735-kV transmission system.
It involves:
The project has been approved by both levels of government and is now subject to Section 22 of Chapter I of the Environmental Quality Act.
The estimated cost of the project (line and substations) is $115 million. Construction is scheduled to start in July 2010, with commissioning in July 2011.
To learn more about the project, consult the Documents section above.