Hydro-Québec’s Sherbrooke substation, starting point of the 120-kV tie line to Hydro-Sherbrooke’s fourth substation.

Project summary

In order for its distribution system to meet growing needs, Hydro-Sherbrooke will build a fourth 120/25-kV substation in the borough of Rock Forest–Saint-Élie–Deauville.

To supply this new substation, Hydro-Québec will build a 120-kV double-circuit line from Sherbrooke substation, which the company operates in this borough.

Schedule

Public consultation2015-2016
Permitting2017
Construction2018
Commissioning2018