Key project stages

Key project stages

  • Planning (2018)
  • Call for proposals (spring 2019) (in progress)
  • Engineering and procurement (summer–fall 2019)
  • Completion of work (2020)
  • Commissioning
    (late 2020)

Basic implementation timeframe

(Subject to change.)

January 2020

  • Installation of breaker (connection point)
  • Start: Application of energy efficiency measures (Promenade Papineau)

February 2020

  • Application of energy efficiency measures (Promenade Papineau)
  • Start: Detailed engineering and procurement

March 2020

  • Application of energy efficiency measures (Promenade Papineau)
  • Detailed engineering and procurement

April 2020

  • Application of energy efficiency measures (Promenade Papineau)
  • Detailed engineering and procurement

May 2020

  • End: Application of energy efficiency measures (Promenade Papineau)
  • End: Detailed engineering and procurement
  • Start: Clearing and extension of power line
  • Start: Construction of substation
  • Start: Installation of solar panels on buildings along with batteries

June 2020

  • Clearing and extension of power line
  • Construction of substation
  • Installation of solar panels on buildings along with batteries
  • Start : Installation of solar panels on the rooftop of the Centre sportif

July 2020

  • End: Clearing and extension of power line
  • Construction of substation
  • Installation of solar panels on buildings along with batteries
  • Installation of solar panels on the rooftop of the Centre sportif
  • Start : Installation of a charging station

August 2020

  • Construction of substation
  • End: Installation of solar panels on buildings along with batteries
  • End: Installation of solar panels on the rooftop of the Centre sportif
  • Installation of a charging station

September 2020

  • Testing and commissioning
  • End: Construction of substation
  • End: Installation of a charging station
  • Start: Installation of smart home devices

October 2020

  • Testing and commissioning
  • Installation of smart home devices

November 2020

  • Testing and commissioning
  • End : Installation of smart home devices

December 2020

  • Operation

Diaporama

Diaporama Microréseau Lac-Mégantic

  • Progress of the construction of the microgrid substation.
    Progress of the construction of the microgrid substation.
  • Progress of the construction of the microgrid substation.
    Progress of the construction of the microgrid substation.
  • Progress of the construction of the microgrid substation.
    Progress of the construction of the microgrid substation.
  • Progress of the construction of the microgrid substation.
    Progress of the construction of the microgrid substation.
  • Progress on the installation of some 1,700 solar panels on the roof the Centre sportif Mégantic.
    Progress on the installation of some 1,700 solar panels on the roof the Centre sportif Mégantic.
  • Progress on the installation of some 1,700 solar panels on the roof the Centre sportif Mégantic.
    Progress on the installation of some 1,700 solar panels on the roof the Centre sportif Mégantic.
  • Progress on the installation of some 1,700 solar panels on the roof the Centre sportif Mégantic.
    Progress on the installation of some 1,700 solar panels on the roof the Centre sportif Mégantic.
  • Panoramic view of the substation and the solar panels installed on the roof of the Centre sportif Mégantic.
    Panoramic view of the substation and the solar panels installed on the roof of the Centre sportif Mégantic.
  • Solar panels installed on the buildings within the islandable zone.
    Solar panels installed on the buildings within the islandable zone.
  • Solar panels installed on the buildings within the islandable zone.
    Solar panels installed on the buildings within the islandable zone.
  • Solar panels installed on the buildings within the islandable zone.
    Solar panels installed on the buildings within the islandable zone.
  • Aerial view of the microgrid perimeter.
    Aerial view of the microgrid perimeter.
  • Some 1,700 solar panels installed on the roof of the Centre sportif Mégantic.
    Some 1,700 solar panels installed on the roof of the Centre sportif Mégantic.
  • Some 1,700 solar panels installed on the roof of the Centre sportif Mégantic.
    Some 1,700 solar panels installed on the roof of the Centre sportif Mégantic.
  • Some 1,700 solar panels installed on the roof of the Centre sportif Mégantic.
    Some 1,700 solar panels installed on the roof of the Centre sportif Mégantic.
  • Some 1,700 solar panels installed on the roof of the Centre sportif Mégantic.
    Some 1,700 solar panels installed on the roof of the Centre sportif Mégantic.
  • A 225-metre extension of the power distribution line
    A 225-metre extension of the power distribution line