Project schedule

Hydro-Québec wishes to develop this project in collaboration with the communities concerned. The project schedule is intended to inform all stakeholders of what has been completed, what is currently under way and what is to come.

The public is invited to discuss with members of the project team during public participation activities. The team will gather participants comments in order to better adapt the project to its surrounding environment.

Public participation process

Pre-consultation Winter 2018 ‒ spring 2019
Project presentation Spring ‒ fall 2019
Project consultation Winter 2019 ‒ summer 2020
Announcement of the selected project Fall 2020
Public consultation by government agencies Summer – fall 2021
Information on construction work 2022–2025

Environmental process

Description of landscape and natural and human environments 2018
Project notice Spring 2019
Environmental inventories Spring – summer 2019
Development of avenues for optimization Summer 2019 – winter 2019
Project optimization, impact analysis and establishment of mitigation measures Spring 2019 – spring 2020
Environmental compliance monitoring 2022–2025
Environmental follow-up 2023–2026

Engineering, construction and commissioning

Technical studies 2018–2021
Permitting 2022
Line and substation construction 2022–2025
Line and substation commissioning 2023-2026