Kruger got involved in energy efficiency projects under Hydro-Québec's Industrial Initiatives Program – Major Customers. By replacing inefficient power-hungry equipment at its Bromont mill, the firm cut energy requirements by 50%, saving roughly 7 GWh per year for all the projects combined.

Project 1: Replacement of primary centrifugal cleaners in approach systems

The mill's centrifugal cleaners required very high pressure differentials to operate properly, which resulted in pressure drops of 345 kPa. To compensate, a primary mixture pump was used to supply the cleaners. The greater the pressure differential, the more pumping power required and, consequently, the greater the energy expenditure.

Cleaners with a smaller diameter were installed, resulting in a reduction in pressure drops of about 160 kPa. The result is reduced energy consumption by the pumping system that supplies the three paper machines.


Project 2: Replacement of level control valves on high-consistency pulpers

A VFD was installed on the pumps so that the pumps, rather than the control valves, maintain pulper levels, thus reducing the pumping power required.
Image : Kruger
Cost of projects
$1,400,000
Financial assistance from Hydro-Québec
$1,000,000
Actual cost
of projects

$400,000
Thanks to Hydro-Québec's financial assistance, the payback period was reduced from 5.15 years to 1.5 years.

“Working with people from Hydro-Québec was excellent from all points of view. We are ready to do it all over again.”

– Denis Lafrenière, general manager of Kruger's Brompton mill