| Date |
Facts |
| September 2008 |
Pumping ends at the temporary dike, and excavation of the Eastmain-1-A powerhouse water intake begins.
Concrete work begins at Eastmain-1-A powerhouse.
Construction of Rupert dam and retaining structures continues.
|
| August 2008 |
Rock excavation ends at Eastmain-1-A powerhouse.
The temporary dike’s enclosure is being pumped to dewater the site of Eastmain-1-A powerhouse’s water intake.
Construction begins at Rupert dam.
Construction work begins on the Sakami canal. |
| July 2008 |
The Rupert spillway is only a few days away from becoming the Rupert River’s diversion route. The water will flow through the structure for a short distance before returning to its bed, allowing construction of the cofferdams to continue, and work on Rupert dam to begin.
The 2.9 km of full-face drilling and blasting at the transfer tunnel has ended. Bench excavation to reach the tunnel invert, 10 m lower, is now beginning.
Backfill of the temporary dike at Eastmain-1-A powerhouse’s water intake has been completed. Sheet piles are now being inserted. Since the dike does not have a core, the sheet piles will ensure that it is watertight. |
| April 2008 |
Diversion of the Nemiscau River through Nemiscau-1 instream flow release structure.
Dismantling of the temporary shelter at Rupert spillway.
Start of contract to build the temporary dike that will enable excavation of the Eastmain-1-A powerhouse water intake and penstocks to begin. |
| March 2008 |
Completion of concrete work at the Nemiscau-1 instream flow release structure. |
| February 2008 |
Excavation work resumes at the site of the future Eastmain-1-A powerhouse. |
| January 2008 |
Start of transport and delivery of merchantable timber recovered from land-clearing work in the diversion bays in 2007; between 450 and 500 loads of timber are anticipated.
Concrete work continues at Rupert spillway. |
| December 2007 |
The Direction – Projet de l'Eastmain-1-ASarcelleRupert wishes you a Happy Holiday Season and a Healthy and Prosperous Year in 2008! |
| November 2007 |
End of land-clearing work in the diversion bay section for 2007.
Building of a temporary shelter at Rupert spillway so that concrete work can continue in cold weather. |
| October 2007 |
Start of full-face blasting of the upstream side of the transfer tunnel.
Start of secondary concrete work at Rupert spillway.
About a dozen land-clearing contracts are now underway in the diversion bay section. |