Project summary
Why?
- Enable the development of renewables in the region.
- Support the region’s industrial development.
- Improve grid resilience and reliability in the face of increasingly intense weather events.
How?
- Phase 1: Build a 735-kV substation and relocate existing 735-kV lines.
- Phase 2: Build a 735-kV line extending for approximately 160 km and relocate existing lines.
When?
- Phase 1: 2035
- Phase 2: 2037
Share your feedback
Share your feedback on the project by visiting the interactive map. Our teams are committed to working with the community throughout the entire project.
Project schedule
Phase 1
2024-2026
Draft design phase: Technical studies, environmental assessment, public consultation
2026-2028
Government approvals
2028-2031
Work: Clearing and construction
Phase 2
To be confirmed
To reach us
We’re very keen on keeping the lines of communication open. Please send us your questions and comments about the project.
Email us
Info‑Project line: 1 866 388‑1978
Mélanie Gagné
Advisor ‑ Relations with First Nations and Inuit
Info‑Project line: 1 418 294‑9988, ext. 2121
Reinforcing the main transmission system – Côte‑Nord [in French only]
Would you like to be informed about project progress and the consultation activities that have been scheduled?