To meet growing electricity demand in downtown Gatineau, Hydro‑Québec will be reinforcing and improving the long-term operability of its distribution system.
To achieve this, Hydro‑Québec will be undergrounding existing overhead distribution lines between Val‑Tétreau substation and Rue Eddy.
A new underground concrete duct bank (roughly 2 km long) to hold the 25-kV lines will be installed.
Preliminary work will begin in fall 2023. Construction of the underground concrete duct bank and electrical works will last from May 2024 to December 2025.
The undergrounding of the existing line means that Hydro‑Québec will be able to dismantle an overhead distribution line that runs between Val‑Tétreau substation and Hull‑2 generating station, along with an overhead transmission line that is no longer used.
Discussions with stakeholders | January 2022–February 2024 |
Communication with the public | November 2023–January 2026 |
Land clearing | November–December 2023 |
Construction of the concrete duct bank and electrical works | May 2024–December 2025 |
Commissioning | December 2025 |
Dismantling of overhead lines | As of January 2026 |