Undergrounding of 25-kV Power Lines Supplying Downtown Gatineau

Project overview

To meet growing electricity demand in downtown Gatineau, Hydro‑Québec will be reinforcing and improving the long-term operability of its distribution system.

To achieve this, Hydro‑Québec will be undergrounding existing overhead distribution lines between Val‑Tétreau substation and Rue Eddy.

A new underground concrete duct bank (roughly 2 km long) to hold the 25-kV lines will be installed.

Preliminary work will begin in fall 2023. Construction of the underground concrete duct bank and electrical works will last from May 2024 to December 2025.

Associated enhancements in the area

The undergrounding of the existing line means that Hydro‑Québec will be able to dismantle an overhead distribution line that runs between Val‑Tétreau substation and Hull‑2 generating station, along with an overhead transmission line that is no longer used.

  • Removal of 9 transmission towers
  • Removal of 14 distribution towers
Project schedule
Discussions with stakeholders January 2022–February 2024
Communication with the public November 2023–January 2026
Land clearing November–December 2023
Construction of the concrete duct bank and electrical works May 2024–December 2025
Commissioning December 2025
Dismantling of overhead lines As of January 2026

For more information

If you have any questions, comments or concerns about the project, please feel free to contact us.

Info‑Project line

1 800 465‑1521
ext. 6022

Contact person

Caroline Milliard
Advisor – Community Relations