Key milestones in the energy transition project

2017

Project to recover residual heat from the Hydro‑Québec thermal plant to meet the energy needs of the integrated health and social services centre (CISSS) (resulting in 1,555 fewer tonnes of GHG emissions every year)

2018

Announcement of the connection of Îles‑de‑la‑Madeleine to Hydro‑Québec’s main power system through Gaspésie

Planning for 2019–2021

  • Implementation of a microgrid
  • Connection of two 3.2-MW wind turbines to the grid

Planning for 2025

  • Connection of Îles-de-la-Madeleine to the Hydro-Québec grid by means of two subsea cables
  • A 94% reduction in GHG emissions

Project schedule

Hydro-Québec wishes to develop this project in cooperation with the communities concerned. The project schedule is intended to inform all stakeholders of what has been completed, what is currently underway and what is to come. Everyone is invited to speak with the project team during public participation sessions. The team will collect comments from participants in order to help better adapt the project to the surroundings.