Appalaches-Maine Interconnection
Hydro‑Québec’s selected line route
In summer 2019, Hydro‑Québec filed an environmental impact assessment (in French only) with the Ministère de l’Environnement et de la Lutte contre les changements climatiques. The study presents the line route selected by Hydro‑Québec for the project.
See visual simulationsDescription of line route selected
The selected line route crosses these municipalities
Environmental approach and project optimization
Environmental approach
Our decision to select this route was made based on an environmental approach involving the following steps:
- Describe the environment.
- Analyze the technical and environmental constraints as well as the sensitive elements.
- Develop a route.
- Assess the impacts.
- Identify appropriate mitigation measures.
- Agree on the follow‑ups to be conducted once the new line has been commissioned.
These steps, which were carried out in collaboration with the host community helped us to develop a solution and then adjust and refine it based on specific regional realities
Project optimization
As a result of numerous exchanges with host communities, the following modifications have been made to the project so far:
- The route of the approximately 24‑km segment of the new line in the Du Granit MRC has been relocated to protect woodlands or follow lot boundaries.
- To the extent possible, the future tower sites have been determined in accordance with landowners’ requests, to avoid valued elements on their properties.
- The line route has been adjusted to ensure the safe coexistence of the power line and the region’s extensive logging operations.
- The commitment has been made to plant shrub species that are compatible with the future power line to limit the impact of land clearing operations on certain properties.
- The project schedule has been adjusted to take the sugar bush season into account
Technical characteristics of the planned line
- Hydro‑Québec has developed a new family of towers for this project: the conductors are located on one side only, thus reducing the width of the right-of-way to be cleared
- Each tower will be made up of a positive pole (+320 kV) and a negative pole (−320 kV)
- Each pole will be equipped with two conductors
- The line will be supported by approximately 320 towers
- The average distance between towers will be 325 m
- The right‑of‑way to be cleared will be 43 m wide where the line runs alone (27 % of the line route) and 10 to 25 m wide where it is paired with an existing line (73 % of the line route).
Power line in a new corridor between Nantes and the crossing point
Visual simulations
Legend
-
Viewpoint
-
Planned tower -
Line route selected -
Tower for the line route variant -
Appalaches substation -
Crossing point
Info-Project – Appalaches-Maine Interconnection
Stay informed on the stages of the project and the progress of work.
Subscribe to Appalaches-Maine Interconnection newsletter