Substation construction

In anticipation of construction, geotechnical studies and other preliminary work—including excavation, compacting and earthwork—were carried out at the substation site. The next phase will consist of the construction of the civil engineering structures, including the substation building and the concrete plinths supporting the substation equipment, in addition to the transformers, which lower the voltage for distribution to customers.

Building the supply line

The construction of the supply line will begin with laying the tower foundations. The towers will be assembled on the ground and then erected, followed by conductor unwinding. The line will be inspected before it is commissioned. Finally, site restoration work will be carried out, which includes cleaning up the work areas, leveling the ground, filling ruts, dismantling temporary access roads and reseeding the site if needed.

Underground distribution lines

The civil engineering work on the underground distribution lines will be undertaken in three sections, each with its own timetable: Saint-Eustache, Deux-Montagnes and Sainte‑Marthe‑sur‑le‑Lac.

The planned work includes excavation, backfilling, and pouring concrete in the public right-of-way so that duct banks and cable vaults can be put in. It also includes drilling to install the concrete-encased ducts and site restoration.

Once the civil engineering work has been completed, Hydro‑Québec will lay the cables.

Diaporama

Diaporama pour le projet Patriote Substation

  • Building the foundations: 315‑kV segment
  • Excavation for fondations
  • Laying foundations of the section of the substation with 19 25‑kV feeder bays
  • Construction of the foundation of substation areas for the 25‑kV feeder bays
  • Aerial view: Des Patriotes construction site
  • Delivery and unpacking modular prefabricated building
  • Aerial view: Installing the prefabricated building