Conversion of De Lorimier Substation to 315/25-kV and new 315-kV Underground Lines
Construction - substation
Work progress
Construction work on the substation is proceeding and commissioning is slated for 2018.
Work currently underway – 2018
- Continuation of civil work
- Building exterior finishing
- Delivery and installation of electrical equipment
- Finishing and landscaping
Work schedule
Monday to Friday, 7 a.m. to 7 p.m.
On certain days, the work may continue until 10 p.m. on weeknights and from 7 a.m. to 3:30 p.m. on Saturdays.
We are aware that some of the work that must be carried out in the evenings may inconvenience you. We apologize for any disturbance and thank you for your understanding.