Continuation of dismantling operations

Dismantling operations will continue from March to June 2021.

Commissioned in 1967, the 120‑kV underground line between Saint‑Maxime and Marie‑Victorin substations has reached the end of its service life. Hydro-Québec rebuilt its first circuit in 2007 and its second circuit in 2019 to ensure the long-term operability of the power grid.

The reconstruction of the power line will ensure the reliability of the electricity service for approximately 12,500 customers in the Longueuil terminal, Université de Sherbrooke and Longueuil city centre sectors, and on Île Sainte-Hélène and Île Notre-Dame.

The last step of the project is dismantling the underground cables and electrical equipment of the old line.

Schedule for the last stage: Spring 2021

The environment: a top priority

The old line will be dismantled in accordance with current environmental standards. The splice vaults and drainage chambers will be decontaminated and the excavation work will be monitored by environmental experts to ensure compliance with laws and regulations.

Project schedule

2021

Dismantling of the remainder of the Saint‑Maxime–Marie‑Victorin line.

2020

Priority dismantling of a line segment under Boulevard La Fayette.

Fall 2019

Commissioning

Spring‑summer 2019

Construction of the new line

Winter 2018‑2019

Information on the selected solution

Info-Project – Reconstruction of the 120-kV underground Marie-Victorin–Saint-Maxime line [in French only]

Stay informed on the stages of the project and the progress of work.

Subscribe to Reconstruction of the 120-kV underground Marie-Victorin–Saint-Maxime line [in French only] newsletter