IQ‑N‑001 – Voltage Schedule
Generator Operators (GOP) must ensure voltages and reactive power of their facilities are
monitored, controlled and maintained in real-time to preserve equipment integrity and reliable
operation of the transmission system.
IQ‑N‑002 – Operational data specification
The Reliability Coordinator (RC), Balancing Authority (BA) and Transmission Operator (TOP)
maintain a documented specification for the data necessary to fulfill their operational and
planning responsibilities. Registered entities that have facilities monitored by the Reliability
Coordinator must respect the requirements and procedures for reporting information and data
needed to operate the transmission system of Québec:
IQ‑P‑001 - Real and reactive power verification
Generator Owners and Operators must periodically verify the maximum real and reactive power of
their facilities included in the Main Transmission System (RTP) as per the procedure below:
They must submit their results using the form below: