Hydro-Québec wishes to develop this project in collaboration with the communities concerned. The project schedule is intended to inform all stakeholders of what has been completed, what is currently under way and what is to come.

The public is invited to discuss with members of the project team during public participation activities. The team will gather participants comments in order to better adapt the project to its surrounding environment.

Project development phases

Draft design
Draft-design studies Underway since spring 2018
Project (*this schedule will be revised accordingly to the progress of the draft-design studies.)
Permitting 2020
Construction 2020-2021
Commissioning 2022