315/25‑kV Saint‑Jean Substation and 315‑kV Supply Line
Project overview
The first Saint-Jean substation was commissioned in 1957, in Dollard‑des‑Ormeaux, at the intersection of boulevards Saint‑Jean and De Salaberry. It supplied electricity to part of the cities of Dollard-Des‑Ormeaux, Pointe-Claire, Kirkland and Beaconsfield, serving about 10,000 customers. Since the facility is over 50 years old, most of the substation’s 120/12‑kV equipment needed to be replaced.
Hydro-Québec rebuilt the 315/25‑kV substation to meet future growth in demand. The new substation, which is largely on the site of the original substation, is supplied by a new 315‑kV line from Sources substation, less than 3 km away. This line was built in a right-of-way where power lines were already located. This project is part of the transmission system modernization on the island of Montréal to help meet increasing demand and ensure the long-term operability of facilities.
Cooperation with the community
A working committee made up of representatives from Hydro-Québec and Dollard‑des‑Ormeaux was created, and met several times to discuss:
- The configuration of the future substation
- The type of tower used
- Tower placement in order to minimize the impact on residents along the right-of-way
- Planned landscaping in the right‑of‑way and around the substation
In 2018, Hydro‑Québec held an information session at the Dollard‑des‑Ormeaux Civic Centre to present the conclusions of the committee’s work. Between May 2017 and October 2018, 12 meetings were held, during which the project was improved to the satisfaction of all.
More to discover!
Enhanced urban biodiversity, improved quality of life and active mobility were at the heart of the right-of-way development project.
Find out more about the new facilityProject schedule
Spring 2018
Substation construction
Fall 2019
Line construction
Late 2020
Commissioning of the new facilities
Summer 2021
Right-of-way planting

To reach us
Write to us
Community Relations – Montréal