Vallée-du-Saint-Laurent

This study area encompasses the Capitale‑Nationale (MRC of Portneuf), Mauricie and Lanaudière regions.

Come meet our team

You are invited to information sessions on the Evolution of the Main Transmission Network project – Vallée-du-Saint-Laurent. We will present an update on the project in your region. We hope to see many of you there!

Tuesday, June 9

From 5 p.m. to 8 p.m.

Sainte‑Christine‑d’Auvergne

80, Principale Street
G0A 1A0

Thursday, June 11

From 5 p.m. to 8 p.m.

Saint‑Adelphe

150, Baillargeon Street
G0X 2G0

Tuesday, June 16

From 5 p.m. to 8 p.m.

Saint‑Élie‑de‑Caxton

52, chemin des Loisirs
G0X 2N0

Thursday, June 18

From 5 p.m. to 8 p.m.

Rawdon

3712, St‑Patrick Street
J0K 1S0

Virtual meeting

Monday, June 8, 6:30 p.m. to 8:00 p.m. – Portneuf region

Virtual meeting

Wednesday, June 10, 6:30 p.m. to 8:00 p.m. – Mauricie region

Virtual meeting

Monday, June 15, 6:00 p.m. to 7:30 p.m. – Lanaudière region

Project summary

Why?

  • Enable additional electricity to be transmitted from northern and eastern Québec.
  • Increase the transit capacity of existing 735‑kV lines that are operating at full capacity.
  • Secure the electricity supply to major load centres.
  • Improve grid resilience and reliability in the face of increasingly intense weather events.

How?

  • Build two 735‑kV substations and approximately 200 km of 735‑kV lines.

When?

  • 2032

Towers

Transmission towers support the high-voltage conductors of overhead power lines. Their shape, height and sturdiness (mechanical strength) depend on the stresses to which they are exposed. For the Vallée‑du‑Saint‑Laurent project, mainly four-legged towers and guyed V- towers will be erected.

Get more information on these types of towers

The right-of-way of the planned line

A right-of-way is the cleared corridor under power lines. It is important to maintain a safe distance between the conductors making up the line and the surrounding vegetation. Transmission lines are not covered by an insulating sheath. Instead, the air around them provides insulation. So, it's important that nothing come close enough to the lines to create an electric arc.

The right-of-way is also used to install, operate, maintain and repair overhead and transmission lines safely.

The width of a right-of-way depends on the voltage of the line, among other criteria. The higher the voltage of the line, the greater the clearance required and the wider the right-of-way.

For the Vallée‑du‑Saint‑Laurent project, the line routes under study run along existing lines for most of their length. This will reduce the total width of the rights- of-way by about 20% to 30%, in turn reducing the clearing required.

Typical clearing for the planned right-of-way

Project schedule

2024-2026

Draft design phase: Technical studies, environmental assessment, public consultation

2026-2028

Government approvals

2029-2032

Work: Clearing and construction

Documentation

Substation in D’Autray MRC

Information bulletin

Maps

Stage summaries

Media

To reach us

We’re very keen on keeping the lines of communication open. Please send us your questions and comments about the project.

Email us

Info‑Project line: 1 866 388‑1978

Yannick Charette

Advisor ‑ Relations with First Nations and Inuit

Info‑Project line: 1 418 294‑9988, ext. 2121

charette.yannick@hydroquebec.com

Strengthening the main transmission system – Vallée-du-Saint-Laurent [in French only]

Would you like to be informed about project progress and the consultation activities that have been scheduled?